Train 18 memoirs: The wise doth know he is foolish and vendors as partners in a public procurement regime?
Excerpts from Chapter VII & VIII:
Around
early April 17, everyone in ICF knew that we meant business and something
unique was going to happen. The core team knew they were about to start an
exciting journey to build a modern train set from scratch; the first time a
project of this magnitude was ever attempted on IR.
Where were we?
We followed up on the multiple meetings that
we held from January onwards with a more focussed approach. We had a vast
reservoir of knowledge as nearly all the countries, except France, had moved to
the concept of distributed power train sets with under-slung electrics and only
a cab and no power units at each end.
Vavre and Srinivas had gathered a vast pool of information. They had
also interacted with the main likely manufacturers and suppliers, in India, and to the extent required, abroad; it was imperative that ICF developed close
conjunction with competent manufacturers in the country. Our design had to be
suited to our conditions and realities.
Idle
paper experts would always come to us brimming with such ideas. Not because
they had any insight in the concepts but because they had merely seen or read
about them. It was a gamesmanship based on a fad and their suggestion would not be serious, per se. I remember making a presentation in Board before we got the sanction where
many casual attendees from Board would indulge in attention-grabbing,
diversions and red herrings. We would handle that as we saw fit at that
time but we were clear that ours would be a no frills design. A
design of a modern train with features which gave us the best bang for the
buck. We had to steadfastly work on the principle of ‘the best is the enemy of the
good’ and ignore such features as:
· Design upgradable to
220 km/h test
· Tilting coach concept
· Articulated shared bogies/Jacobian concept
· Aluminium body
· Extra long bullet-nose like Japanese high-speed trains
· Tilting coach concept
· Articulated shared bogies/Jacobian concept
· Aluminium body
· Extra long bullet-nose like Japanese high-speed trains
The primary requirement was to design a train
set capable of operation at 160 km/h and validation testing at 180 km/h. Before
any detailed work could start, we had to have clarity about the nature of the
train, i.e., a day train like Shatabdi
or an overnighter like a Rajdhani. Given
that 160 km/h operation was possible only on very few small sections of IR, perhaps
only on Delhi-Bhopal section (approx. 700 km), it had to be a day train, a faster
equivalent of Shatabdi.
The immediate task was to make a
detailed table listing the status in respect of the main features of the
proposed train set and break them down in three categories: 1) area where we
were there or almost there, 2) areas where we could be there with judicious selection of
vendors, including import, but strictly as per specifications and drawings
developed by ICF and 3) areas in which we could be there only with handholding
by some superior intelligence.
I
had mentioned that we had made a matrix earlier too but that was very
basic. We now prepared an exhaustive matrix, assigning a category to each item.
We had to be particularly careful that we did not overestimate our capability
in our zeal and candidly brought out the gaps between our wish and the reality. It is
impracticable and unnecessary to reproduce the matrix fully and I give here
only a representative summary.
Item
|
Where were we?
|
Car body shell design and manufacture, including
painting
|
We did it
all the time.
But not
to the quality and accuracy we must have if we had the intention to match
international standards.
We would
need hand-holding as we design the car body as well as its fixtures, tooling and processes, which would be amenable to more accuracy and better
quality. We will need supervision during manufacture as well.
|
Fully suspended traction motor bogie fit for 180
km/h
We have
neither a coach bogie design on IR to run at 180 km/h test speed nor a bogie
to accept fully suspended motors. Do we have the capability to design one?
|
We had
designed many bogies in the past. If there is any Design Wing on IR which could
take up this critical and massive work, it was ICF.
What IR,
including RDSO, has done so far is tinkering around a borrowed design, be it
locomotives or coaches. A good example, we had not been able to even tweak the
LHB bogie to accept alternators, let alone traction motors. This was a
different ball game; we had to design a bogie from scratch.
|
Efficient 3-phase IGBT propulsion with
regenerative braking
|
Almost
there. On evaluation of 3-phase electrics ordered by ICF and thanks to some
great R&D work by an Indian company, it was heartening to note that this,
the most expensive part of the train, could be developed indigenously with
some extra R&D effort. It was understood that ICF would establish seamless
working and infuse synergy among all the parties.
|
…..
(Rest of the matrix withheld....will appear in the book)
…..
The list, as I pointed out, was much longer but we were able to identify capable and willing Indian companies for most of the items to manufacture as per our drawings and specifications. In case import looked inevitable, we would go back to the drawing board and try to tweak the requirement to enable sourcing in India. We had to keep the cost in control as it was imperative that the prototype got built at around 50% of the ruling international price for the same. What Lord Bardolph in Shakespeare’s King Henry IV says, was apt for us here, “When we mean to build, we first survey the plot, then draw the model; and when we see the figure of the house, then must we rate the cost of the erection; which if we find outweighs ability, what do we then but draw anew the model.”
But
what about areas which had this significant gap between our capability and the
requirement? Well, firstly, it was more important to identify these gaps
truthfully. Remembering Shakespeare
once again,
“The fool doth
think he is wise, but the wise man knows himself to be a fool”, says Touchstone in As you like it.
I
made it clear that while our sights were high, we would be rooted to the
ground reality. We would not be foolishly wise but wisely foolish. We had to remember it all the
time. Better be a fool now and wiser later than to be wise before the deed is
done.
…..
(Content withheld....will appear in the book)
…..
When
the gap between the requirement
and our capability is sought to be bridged through the services of some superior intelligence, as I called it, there
are no impediments in engaging design consultants. Such consultants, not
being a member of a big multi-national major, with eyes on future supplies,
have an equal stake in our delivery on design and build. They have no stake in
future supplies of components like companies imparting ToT. Their aim is only in
delivering a good design and If handled with a sense of purpose, they can be
programmed to first determine our capability and mould their concepts and
designs accordingly. The process of learning in this arrangement, apart from
completing the contracted design and manufacture exercise, is more
comprehensive. The ICF design staff would get an upfront education to imbibe
the nuances of all design concepts and processes, the know-why. Subsequently, when the designs would be taken to
manufacturing, a deeper understanding of know-how, through continuous two-way
synergy with the consultants, would also develop. I saw it happen with our
teams at ICF; they would gain a lot in capability which should help ICF a lot
in future projects. Moreover, this being our first enterprise, there would be
great scope to improve the future builds. The consultants are very open in
looking at all feasible improvements, including sourcing and new developments in India than a multi-national engaged for ToT could or would ever be.
We would clearly stipulate in our consultancy contracts that our
team would work with them. Every single line they drew or every single word
they wrote would be done along with us so we got to know the why elements of all the designs. At the
end of the day the complete ownership of drawings and specifications developed
in the process would rest with ICF, irrespective of the inputs from the
consultants. For the first time on IR, we
would be the real master of the Intellectual
property rights (IPR), for whatever it would be worth in future; full
ownership of the product would be with us, precluding any need to keep
approaching some TOT contractor sitting abroad.
The picture was clear. It was time to plan actions and move
quickly towards execution as Benjamin
Franklin had said, “By failing to prepare, you are preparing to
fail.” The lucxury of planning with full composure was not available to us and the speed of execution
had to be supersonic. At this time I used a ploy; I told the team that we must
turn out the prototype before the CRB retired, that is, July 2018. I was the boss so no one laughed at me. But the
disbelief and amusement on their faces could have translated to, “This guy has
gone bonkers.” Yet, Trivedi, with the other key member of the team, started to deal separately with the
time line issues. It worked. Whether to get the monkey off their backs, or
otherwise, our Planning and Design men put up a plan, with impressive Gantt
charts, which showed us that the prototype could be out in June 2018. God knows
who was fooling whom but Ghalib
gauged the situation for us and Fani
Badayuni even invited a preacher:
…..
(Content withheld....will appear in the book)
…..
But
June 18 was less than 15 months away and not a single contract was in place
yet. Was my team going to fling Shakespeare
at me as we approached June 18, leering Player
King in Hamlet, “Our
wills and fates do so contrary run that our devices still are overthrown. Our
thoughts are ours, their ends none of our own”. So much for my poor
ploy!
In
any case, the spirits in ICF were soaring high. As we began our work, it was
imperative that a buzz about the project be created internally as well as
externally. The duo of Vavre and Srinivas had constructed some narratives,
based on thorough study and material culled from across the globe on the trend
of train sets; they prepared a series of presentations on the project, including ones for the
Board. They took a series of meetings, stressing the outline and proposed time
line of the project. Everyone in the team, including the members from Stores
and Finance wings were sensitized about the Train 18 project. Indeed, everyone,
barring some, was rising to the
occasion. It was clear across the departments that ICF was attempting something
novel and they wanted to be a part of it. So how did we start?
Item
|
This is how we started
|
Car body shell design and manufacture including
painting
|
We had
to go a quick consultancy contract on a European or Japanese firm, as they
are the trailblazers, for making our designs, tooling and processes amenable
to more accuracy and better quality. We zeroed in on three companies, one in
Poland and two in Switzerland, who did similar work for European majors. In a
quick process, the consultancy contract was awarded to the Polish company.
|
Fully suspended traction motor bogie fit for 180
km/h
|
In a
dissimilar exercise, a novel way of combining consultancy with a major
procurement case was in hand. We moved quickly to finalize the contract,
incidentally, on the same Polish company.
|
Modern 3-phase IGBT propulsion
|
The
train set electrics were tendered for as a part of separate electrics tender
worth more than Rs 1000 crores, which was languishing for nearly a year due
to indecision. Indecision or delay was not an option any more. We invited fresh bids and without any
pressure on anyone for any particular result, the tender was finalized in
three months flat. It was for the first time that ICF had awarded a contract
of this magnitude. Earlier Board dealt with such contracts and the time-line norm
for finalization used to be in the range of two years.
|
…..
(Rest of the matrix and content withheld....will appear in the book)
…..
Every
organization has people who do not care for action and delivery. They sit in
their cubbyholes concerned about staying safe or working on some personal
agenda. They cavil, equivocate or procrastinate, but never say Yes. Doesn’t
that remind you of jalebis, the syrupy Indian sweet which
looks like never-ending coils? Whenever I came across any such instance,
I would call for the file, make my own judgement and if indeed there were some delaying the case unnecessarily, invite them to my room, order jalebis and offer it to them, saying
that they had really earned this distinction. I added that since it was a great honour,
even diabetics had to eat those jalebis.
Not that I wanted officers to earn jalebis,
but cannot deny that watching the consternation of these jalebi-smitten guys was
good entertainment for me and Babu. Whether the officers concerned improved
their working is a moot question but the message certainly got conveyed.
In short, by
mid-2017,
· The three major
consultancy contracts were in place:
·
New
bogie design with fully suspended traction motors
· Improvements
in design, tooling and processes for shell, including supervision during
manufacture
·
Interior
styling concepts
· The
most crucial major contract for supply for electrics and allied systems was
placed on an Indian company
· The
preliminary design work had started at ICF in full swing
· Cases of
Contracts for bought
outs were moving at a fast pace, for import as well
as local
Around June 2017 our PR department prepared a write-up and when
it was run through me before release, I could see that M/s Vavre and Srinivas
did not find the new Train 18 time line as daunting as I did. I reproduce this
write-up here.
ICF
plans to turn out the prototype Train 18 on 30th June 2018 which
would be a semi-high speed (180/160 Km/h)
train set with fast acceleration and world-class passenger amenities........
(Rest of the matrix and content withheld....will appear in the book)
provide a fast and wholly new
travel experience.
Bingo!
They got it right except for the first line. Or had they really purchased my
gimmick hook, line and sinker? I know they would keep their noses to the
grindstone and let everyone go the extra mile but still, what an uphill battle! My ruse was giggling back at me, confounding me some. A well-wisher confidante,
an old ICF hand, comforted me, “Saar! No worry, saar. In ICF, the target for
June 18 turn out is very much achievable.”
Indeed!
I am sure he had not read Much Ado but I bunged Bendick
at him, nevertheless, “I would my horse
had the speed of your tongue’’.
One of the key to our success would lie
in awarding effective contracts for development, manufacture and supply of
equipment and components, by ordering on an array of vendors through the Public
Procurement Policy. The questions which arise are:
Can you
make your vendors your partners?
Is the Public Procurement Policy a disabler or an enabler?
At the end of the day, our Train 18
strategies were working fine and even getting spun off to all other areas. The
consultancy and procurement contracts were getting finalized fast. In this
diversion from the main Train 18 story towards procurement of stores, let me
dilate upon the oft-repeated cliché in govt. organizations, more as a lip
service pretension, and not as a governing mantra, “treat your vendors as
partners”.
Let me go back some twenty five
years when I was working as a Joint Director in RDSO, the premier R&D wing
of IR. Every day, a large number of industry executives would visit our
directorate and one would see them standing in the corridors, waiting for
audience with some officer or the other. Some would be seen sitting on the
attendants’ stools. I always found it rather embarrassing. One of the
toilet doors in the common wash area was broken for years and I once saw a
foreigner inside with his head hidden in his palm; the pressure of Delhi belly
had perhaps got the better of his sense of indignity. Were we going anywhere
with this kind of a set up with important visitors not even offered basic
courtesies? Well, thankfully the then boss of my directorate got one room
converted into a make-shift visitors’ room which was somewhat of a novelty in
this sarkari type office
and well, as I saw it, something was better than nothing. The situation rankled
but many of my colleagues were least concerned about all this; their take,
“These people are here for their work, why should we bother about them”. Were
we an organization for dispensing favours or were we here to collaborate with
industry and develop cutting edge products for IR?
Let’s move forwards to some 16/17 years back when I was
Chief Design Engineer at Diesel Locomotive Works, Varanasi. One day I had an
important tender negotiation meeting and the convenor informed me that the GM of the
concerned firm had arrived and that I should come to his room. I went to his
room and on the way met the GM gentleman standing outside the room. The
committee discussed the tender at some length, interspersed with many
pleasantries and small talk. Eventually after more than an hour, the gentleman
was called in and before we could begin, he said, “Sirs, you people are big
officers of railways but even I am the GM of a reputed company. If I have to
stand outside your room for hours, I take it my stride in the interest of my
company but the disgrace rests entirely on your exalted status and your
organization, not mine”. We were speechless but I am sure the others forgot it
within no time. I, however, thought that what he said was so right. Since then,
wherever I have worked, I have made sure that visitors are treated with dignity
and not made to wait; if waiting was unavoidable, as indeed was frequent, they
would be seated in a proper visitors’ room. And if the wait was going to be
long, I would invite them to be seated in my room itself on sofas/side chairs
till I became free to meet them. Big deal? Not at all. But the message was certainly very positive, “You are here to find ways to partner with us,
to collaborate with us and not to collect favours”. That GM gentleman
is a friend till date and we have done many projects together, but, of course,
entirely on merit of the case.
This change in our outlook and in our disposition that our
industry partners were our companions in an enterprise had to be inculcated at
every level in ICF. We needed to deal with the vendors with empathy and not
indifference. Some
members of the team were already ahead of my thoughts. For example, Srinivas,
was already known to treat the vendors in a very business-like manner but with
remarkable courteousness. I heard only words of praise from all vendors,
cutting across our supply and development chain, about Dash, who would later
take over as CDE/Electrical. Trivedi was also known to transact with our
vendors in a very professional manner. I would like to think that gradually the
interaction with vendors became more professional and business-like and not
that of one supercilious purchaser vis-Ã -vis supplicant
vendors.
We, however, always came
down hard on vendors who in our judgement, were not showing any resolve to
improve. Punitive measure should be exemplary, not routinely customary. We must
follow Angelo from Shakespeare’s Measure for Measure,
“We must not make a
scarecrow of the law, setting it up to fear the birds of prey, and let it keep
one shape, till custom make it their perch and not their terror.”
…..
(Content withheld....will appear in the book)
…..
We,
like other government organisations, had to follow the Public Procurement
Policy provisions and guidelines. There are a lot of misconceptions about these
policies; the prime misgiving among purchasers and suppliers being the intent
and execution. Most people seem to believe that the policy prevents you from
buying the best and L1 syndrome guides you to go to the lowest bidder, with
quality and durability of the product given a short shrift. This is far from
the reality. The policy guides you to make sure that public funds are used
judiciously and that some form of level playing field is available to aspiring
suppliers vis-Ã -vis the established ones. The government executive
dealing with public money must have the courage of conviction to decide which
product(s) would be the best for an application and then go about ensuring that
with transparent and cogent arguments. The policy does not prevent you from doing it; on the
contrary, it empowers and enables you to do it.
Many
executives find it surprising but it enables you to decide a case even if you
get one bid in a tender, given certain condition. Shakespeare speaks through
Hamlet, “Why, then, ’tis none to you, for
there is nothing either good or bad, but thinking makes it so.”
Absolutely. If your objective is transparent in what you want to purchase or
develop, and do it with a clear reasoning for who and why, there is every feasibility of achieving it, even in a
government set-up.
The
problem is that many government executives want a procurement solution on a
platter without them having to exercise their judgement and show firmness of
purpose; they prefer to choose the easy way out of going with the least
controversial path. It is always safe to follow the path of least resistance
and let the sense of propriety be twisted to justify sub-optimal procurement
action; the omnipresent excuse would be that they could not work like a top
executive in a private firm who was entitled to do it straightway and no
questions asked. But they forget that such an executive also carries
responsibility towards the shareholders, board and bottom line of the company
and his decisions are not whimsical. At times even the boldest executives may
find it difficult to judge what would be right; they tend to take the ubiquitous
band-aid solution to avoid complaints, complications and accusations. Remember,
the glitches and bugs in the Obamacare software in the initial days? Even the
most powerful person on earth, the then President of the US, Obama, lamented
that execution of the health policy had issues as the agency assigned the software
job was chosen through a state procurement policy! But such cases should be
exceptions, not a de rigueur.
…..
(Content withheld....will appear in the book)
…..
In
all critical areas, we had to order the items from established and proven
vendors who had either supplied for train sets globally or were truly competent
to do so. In addition, the emphasis to procure from Indian vendors as far as
feasible was not to be forgotten. Most of the team members at ICF, including
those from Stores and Finance realized this and did not shy away in deviating
from the regular sarkari way of
dealing with Stores cases. I cannot recall cases, barring of course some
handful of them, in which the order was placed on someone who failed to react and
deliver in time with quality. Yes, there were some officers who would not see
straight and find all kinds of excuses or reasons against bold actions. Their
way of conveying their negativity, disguised cleverly under fake positivity,
would be something in the fashion of this great philosophical ghazal
of Ghalib:
Na tha kuchh to khuda tha, kuchh na hota to khuda hota
Duboya mujhko hone
ne, na hota main
to kya hota.
Hui muddat ke Ghalib
mar gaya par
yaad aata hai
Wo har ek baat par yeh kehna ke yun hota to kya
hota.
(When
there was nothing, there was God. If there were nothing, there would still be God.
I am sunk because I am but if I were not there, what would I be? My being is
dead for a long time but I do remember your saying that if it were not so, what
would it be?) Now this is a creation with multiple interpretation in
spiritualism and ways of life so but just look at the literal meaning here.
Getting
over the sporadic negativity was never a major challenge although this form of
nay saying and nitpicking was perhaps more inimical for the project than jalebi-making. Support from Trivedi, at
managerial level, Vavre and Srinivas, on technical issues, and Stores officers
in general was for the asking. With the proper procurement actions bottled up firmly, it was a matter of engaging the selected vendors in the design
process meaningfully; since most of the sub-assemblies and components had some
technical novelty in them, these key vendors had to be an important part of
development. For example, development of a noise-free comfortable
air-conditioning (AC) equipment required development of three prototypes of AC
ducting and complete re-design of the AC units midway of the project even after
approval of drawings. The selected partner, an Indian company with vast
experience on IR and Metros, re-designed the complete equipment and delivered
the same without affecting timelines significantly.
Yes
we can procure what we want through the Public Procurement regime; and from
whom we want and make them our co-travellers in our journey.
I like to take a bow in honour of the bard who wrote these lines
for all us and spoke through Helena in All’s
well that ends well:
"Our remedies oft in ourselves do lie, which we ascribe to Heaven."
(to be continued)
Comments
Post a Comment