Train 18 series 24…sisters of Train 18 and RDSO
The concept of
providing all the equipment, not only for traction and braking but also for
air-conditioning, ventilation and lighting, and indeed everything else, below
the floor was working out. As Train18 neared completion, we could see that this
would revolutionize the way we laid out equipment and sub-assemblies in our
rolling stocks. In any case, we were certain that we had hit upon the right
concept and that we must transfer it to other rolling stocks as far as possible. Back in early 2017, even as the Train
18 work had picked up speed, both Sri Srinivas,
Chief Design Engineer/M and Sri Vavre, the then Chief Design Engineer/E approached me with a grandiose plan to
equip all self-propelled trains with Train 18 clones for bogies and propulsion.
Although the Train 18 project itself was in infancy, they were already brimming
with confidence about the impact it would crate and change the way we designed
rolling stock. It was music to my ears as it had been at the back of my mind
too. I immediately gave them a go ahead, with a smile, saying touché with this
couplet from the poet Faiz:
Agar sharar hai to bharke, jo phool hai to khile,
Tarah tarah ki talab, tere rang-e-lab
se hai**
** if it were a spark, let it enflame or if it were a
flower, let it bloom,
we have so many expectations from the richness of your lips.
Our
design team had started parallel work to adopt and adapt this concept on all
Multiple-Unit self-propelled trains, whether suburban, main line electric or
main line diesel-electric. We had called bids and tied up with three firms to
develop the electrics for these trains apart from the brake system and other
equipment with the condition that these equipment would be kept common with
Train 18 as far as technically feasible and judicious; while one of the firms
was the Indian firm which did all the remarkable works on Train 18, the other
two were new entrants with some promise. In spite of our best efforts, an
existing world major supplier of electrics to ICF had not accepted an order as
they found it very difficult to match the price set by the Indian company. This exercise of Train 18 cloning would help us in driving the future Train 18 procurements to a higher volume
thereby bringing down the price; at the same time, these type of clone trains would
also be upgraded to a more modern and comfortable type.
Basically, we had three sisters on the anvil, and the
work we did on these makes an interesting saga in itself.
The first was the Main
line Electrical Multiple Unit (MEMU) with under-slung electrics employing the
Train 18 bogie with fully-suspended traction motors and suitable modifications
in the suspension elements as the speed of this train would be lower, in the
range of 100 to 130 km/h. A main line self-propelled train which can do 130
km/h speed would be a boon for short distance intercity traffic. What is in
operation today is an outdated MEMU with DC electrics, suitable only for 105
km/h operation; it’s hardly suited to run on 130 km/h routes as it slows down other
traffic. The train would be equipped with good gangways, modern toilets and
many new features for the benefit of passengers.
The
story of MEMUs was hitherto a sordid one till we broke the chronic malaise of
ICF and Rail Coach Factory (RCF) ), Kapurthala accepting the archaic technology
ruling the roost. An attempt to incorporate the latest 3-phase IGBT technology
by both ICF and RCF was a story of imprisonment of the minds of leadership by
procedures and a sham sense of propriety. Transparency and probity in public
procurement are the last resorts of an abdicator; real transparency lies in
doing what is right, howsoever challenging or risky the decision may be. Meaningless
tenders were floated and jalebis were being made for years;
even those who knew the correct course of action were a victim of chalta
hai or saanu ki syndrome. Saanu
ki? Well, it is a rhetorical
question, an interjection. Literally translated from Punjabi, it means, “what (does it matter) to us?”. If our
system makes it difficult and painful to order on the right manufacturers, so
be it, it’s no skin off my nose so why should I stick my neck out?
At
about the same time in 2017 both ICF and RCF opened a bid for 3-phase IGBT MEMU
electrics. We had taken care in our documents to make sure that, at least, the
bulk order would not be bagged by an incompetent, or at least
inexperienced firm; such a firm was likely to experiment at our cost and delay the
project. RCF did not do any such thing. Since it was essentially the same
product that we were going to order, I called their officers and told them of
the pitfalls they were walking into; the reaction was blind denial with their
leader making a cocksure statement that they would build the first 3-phase MEMU
faster than ICF. Abraham Lincoln has said that he did not think much of a man who was not wiser
today than he was yesterday; there were these officers, witnessing glimpses of
effective procurement systems at ICF, but not willing to learn out of misplaced
confidence, cussedness or simply sloth. They went their way and we
ours. We turned out the prototype MEMU with on-board 3-phase electrics in
2017-18 itself and the prototype MEMU with under-slung electrics, the first
sister of Train 18, by November 18. The readers will see some details later. Our
friends in RCF, however, still turn out MEMUs with DC technology and the firm
they favoured with the order for on-board 3-phase IGBT electrics is still
struggling. As for under-slung electrics, they have not even been able to
order.
It’s hardly my place, unlike Jasper Fforde, to declare that there was something rotten in the
state of IR, but let me, at least, be a little flippant and tell him that we
have so many among us who could safely and truthfully say, without the need to
rub their temple like his Hamlet, “I don't know what comes over us. Not all of
a sudden, but nearly always, we have this overwhelming desire to talk for a
very long time without actually doing anything.” Yes, sir. On IR, it can actually see you
through your life time.
The second sister was the air-conditioned Electrical
Multiple Unit (EMU) with
under-slung electrics, again employing the Train 18 bogie with fully-suspended
traction motors and suitable modifications in the suspension elements to suit
the operating speeds up to mainly only 110 km/h but should the need and infrastructure
support it, could be speeded to up to 130 km/h. The train would be provided
such novel features as higher acceleration capability with Train 18 like 50%
powering and sealed gangways going through and through from front to rear cab. The
train would also have many features for a new travel experience for the suburban
passengers. This project was take up mainly to cater to Mumbai area as a loose
policy decision, or at least a vision, had been announced by the ministry to
have air-conditioned local commuter trains in that area.
We had decided to exploit the opportunity of modernizing
the EMUs for Mumbai area in big way. Although the announcement for air-con
rakes was made only for Mumbai area, I knew that once such air-con EMUs are
introduced in large numbers in Mumbai area, there would be a demand from other
areas as well which could not be ignored. There was a good future for the
product and we could actually attract manufacturers of accessories at
reasonable prices. Incidentally, ICF had turned out first of its kind air-con
EMU in 2015 which was a good beginning but the train itself was a bit of a dud.
It did not have enough acceleration to make up for the time lost in opening and
closing of automatic doors; after a struggle for nearly two years in testing
and validation, the rake was finally introduced in service to lukewarm response
and much criticism. One good thing about this project, however, was that it afforded
us a lesson on what not to do in projects. We had, in my opinion unfairly,
burdened the manufacturer of propulsion system for this rake with many new
requirements although they were mainly contracted to develop a simple 3-phase
IGBT system for Mumbai area suburban trains. It was not surprising that they
proved unequal to the task and earned a bad name for themselves and also ICF. A
way, however, had to be found to fast track introduction of air-con rakes in
Mumbai area.
Even as a series of meeting in Board and Research,
Designs & Standards organization (RDSO) were held, deliberating on how to
introduce more and more air-con rakes in Mumbai, I could see that it was
nothing but a Shakespearean saga in play; a tale full of sound and fury, signifying
nothing. I told my team that while it was expedient to keep those at Board
and RDSO in good humour, it was futile to expect any meaningful decision to
emanate from them. I told them to go and read Romeo and Juliet; they would not only enjoy it but come back with the
takeaway to “Go wisely and go
slowly. Those who rush stumble and fall.” Learn to take the time
to appraise our options or consider the consequences of individual actions;
these simple but immortal words of Romeo
encourage us to not to act with haste but make sensible thought-out decisions.
The
pace of technological advancement in the field of trains had accelerated
considerably, thanks to our efforts at ICF. This often led those concerned in
Board and RDSO, including the concerned Member, to injudicious decision-making as
they did not have a good understanding of what ICF was up to or even what ICF
had become capable of. They would end up calling largely meaningless meetings
with rolling stock majors and get even more confused. The options under
consideration were, 1) more of the rakes of type we sent out in 2015 2) partial
air-conditioning of rakes with full air-con rake turned out from ICF to
apportion it between two non-air-con rakes 3) Air-con rakes with a
configuration similar to those planned for Mumbai
Rail Vikas Corporation (MRVC) and thankfully, 4) air-con rakes of the type already
under detailed design work at ICF.
In
spite of all the brouhaha and hemming and hawing, we at ICF were clear that the
air-con suburban train which was going to succeed was the one we were working
on purposefully, the second sister of Train 18.
So what
was this story of MRVC rakes? Another of those stories of first inaction, then
slothful activity and eventually, production of a laboured bid document with a
thousand holes. I will go into the MRVC story some day but there was a
disconnect between what ICF was pursuing and what this RDSO/MRVC document
sought to procure. One of the primary difference was the use of the
conventional EMU bogies instead of the Train 18 clone with fully-suspended
traction motors. This, in my opinion was a retrograde step as the
track-unfriendly conventional bogie would never take the train speed beyond 110
km/h; moreover, it was very maintenance-intensive. Why was RDSO insistent on
this? Because they feared that a fully-suspended traction motor would lead to
water ingress when the water level rose to a certain height in rainy season; a
train can never operate with water level at this height and it was stipulated by
them mainly to safeguard the motors against rise of water level to this height
in a stationary condition. Well they had their view and I had mine; in my
opinion, you should not screw up a design just for a contingency, which ideally
should not even occur, or even if it did, we should be prepared to do a
thorough overhaul to rectify the damages in the motors. While we pursued our
manufacture of the second sister prototype strongly, we had to go with the
RDSO/Board bid documents for a tender for electrics to be procured under the
aegis of MRVC. It’s another matter that we decided to drop this tender, with
good and strong reasons but about that some time later. The jury, as far as I
know is still not out and tender has not been put out yet. The second sister,
on the other hand, would be almost ready by the end of my tenure although
actual turnout was delayed to early February 2019.
The third sister would be a Diesel-Electric Electrical
Multiple Unit (DEMU) with
under-slung engine and transmission, first with the existing traction motors on
bogies and later with Train 18 clone bogie and fully-suspended traction motors.
ICF had already upgraded the electrics of DEMUs with modern 3-phase drive and
it was time to exploit it further to a more modern energy-efficient and
passenger-friendly version. There were, however, question marks as IR had
decided to phase out diesel traction in a big way. As expected, Board was
non-committal. Fortunately, I got to speak at length in one of the meetings
where everyone who mattered was present, including the top gentleman. I
clarified that development of DEMUs was essential as this was an emerging
market for export; we had an order for DEMUs from Sri Lanka for which we were
working strongly. I had my way; it’s not out of place to mention that
eventually this prototype DEMU for Sri Lanka, designed fully by ICF in 2017 and
delivered in 2018, has proved to be successful with reports that it has been
liked better than similar rakes from China.
The readers must
appreciate the level of enthusiasm and hard work that ICF was now capable of;
we are talking of a series of new designs all in a space of two years. New
rolling stocks of great value from the team in addition to Train 18.
I cannot fault the
readers if they carry an impression that I was trying to run down RDSO and
Board. Well, about RDSO first. This is an organization I have worked at for
nearly twelve years, first as Joint Director/Director and later as Executive
Director. It provided me a great opportunity to learn the finer points of
rolling stock engineering; I have no hesitation in acknowledging that a large
part of whatever little I know is because of my stints in RDSO. It also
provided me a great platform to grow in the field of railway engineering and
later in the field of management of large railway projects. RDSO, in my
opinion, used to be an gold mine of railway engineering, which was waiting to
come of age or poised to be exploited for greeter things. Quite the reverse,
however, has happened; somewhere along the way, I dare say particularly in the
last decade or so, RDSO has lost its way. A great organization for application
and assembly engineering, it has fallen prey to people with misplaced
understanding and stupid vision of trying to fashion it as a fountainhead of
new research. Unnecessary hidebound restrictions has stolen it of whatever
creativity it afforded to its officers; they are now busy with mundane vendor
approval processes. New rolling stock designs do not flow from RDSO anymore.
Examples of stark bureaucracy resulting in damage to our own indigenous
technologies abound. It was a given that nothing new in the form of research
would emanate from RDSO but their mainstay, the legacy of development of new
products, mainly in association with industry, is buried in oblivion. The
number of competent officers manning RDSO is legion but the quality of output
has become pathetic. While it has to continue as the central agency for all railway
infrastructure and rolling stock testing and certification, it now derives its
strength from its statutory authority and not from its knowledge or expertise. An
attempt has recently been made to rejuvenate the organization through some
restructuring but it has followed the same old route of wistful thinking,
trying to build castles in the air. There is something called Long
Term Research, which in the context of RDSO is nothing short of an oxymoron.
Then there is field of Quality
Assurance, hardly the job of an institute which should primarily
concentrate on new designs. Incidentally, RDSO has a system of approval of vendors
which places the existing vendors on an unshakable pedestal and established vendors
with pathetic record of quality go unpunished; at the same time truly capable
and frivolous vendors are painted with the same brush. Am I sounding too
vituperative? I hope not but if I do, please remember, I have attributed most
of my knowledge and growth to my stint in RDSO and when I see such an
institution going to seed, how can I hold back? My musings cannot be a sweet
soufflé all the way; some bitter though truthful ingredients have to be added
for variety.
RDSO was like my mother, after
all, there was a time when I would jump at people who denounced or disparaged
it out of sheer ignorance or arrogance. I would love to be able to do so again.
I have my right to look back at its prime, remembering this from the Shakespeare’s Sonnet III:
Thou art thy mother's glass and she in thee,
Calls back
the lovely April
of her prime;
As for Board, it a
very complex question. I have no intention to start analyzing its merits and
demerits as whatever good, or bad, is happening on IR today can be largely
attributed to Board; one can make one’s own judgment. My bad experiences were
perhaps more due to certain officers who were consumed by pretensions, vanity,
jealousy and unfortunately, stark stupidity. We would often think about it. One
of those days, the question of our constant battles with Board came up again
and Sri Babu, the Secretary/ICF smiled and observed that he had seen confrontation
between the GM and Board many times but the present one would easily take the
cake. I thought about it and smiled too, closing the subject with the help of
my chacha
(uncle) Ghalib once again:
Hum
kahan ke daana the kis hunar mein yakta the
besabab
hua Ghalib
dushman aasman apna**
** Whitherto was I
that learned and which skill was I so accomplished in? Without reason, the
heaven has turned my foe!
And why?
Raha aabad aalam ahle-e-himmat
ke na hone se,
Bhare hain jis qadar jam-o-subu, maikhana khali hai**
** The world remains so populated but in spite of absence
of the courageous; the cups and containers of wine are full but the tavern still
remains empty.
(to be continued…)
Sudhanshu Mani sir I am very big fan of you. I think you should come in Mumbai for our 2nd AC local which is underslung equipped motors & generators for flag off at date of flag off.
ReplyDelete