Train 18 series 20...some more on design and train’s progress
I keep digressing so much; I must come back
to some core design and manufacturing issues. As I write, I am faced with a
dilemma a novice chronicler would perhaps always face. What to write and what
to ignore or eliminate? I am not intending to let this story be followed only
by those who understand design and manufacture of railway coaches, or rather not
merely that but engineering processes as such. So going too much into niceties
of design and manufacturing would be too esoteric. I have, therefore, been
trying to bring in design and manufacturing issues and solutions only in dribs
and drab and that too in a rather cursory, not elaborate, manner. I am trying
to build this narrative around a mosaic of all issues usually encountered while
executing a project of this magnitude. Handling of human resources is always
the key and that has taken precedence over knotty technical aspects in my story
such that neither are diehard rail fans disappointed nor are those with wide
interest in things Indian find it stodgy.
To make sure that the entire floor space of
the train would be available for use of passengers with a wide gangway, all
equipment had to be mounted underneath the floor, i.e., mounted below the under
frame members. This had never been attempted earlier in a coach in India. The
complexity of the design and subsequent manufacture can be depicted through a
simple model of one of the under frames, which had a multiplicity of gobs of
equipment packed in it; and imagine, there were six such types in the train of
sixteen coaches!
A large number of newly designed equipment
including a wholly new system of 25KV transmission, under-slung converter, more
powerful transformer, auxiliary convertor, a state of the art computerized
brake system, automatic sliding and plug doors with retractable steps,
efficient air-conditioning system, passenger information and passenger talk
back systems, CCTV network etc. Were, inter alia, equipment which were of a new
generation and obviously new design. Most of this, rather all these systems, not
only needed mechanical compatibility but also an electrical and electronic
marriage with the newly developed heart of the train, i.e., the traction
control and management system. These system integration exercises were not
something new for the ICF team but this time the intricacy as well as the time
line had a much greater degree of difficulty.
As I have written earlier, the ordering was
done very quickly and smoothly; that was, however, half the story. Having
ordered, convincing the selected suppliers, who frequently depend on some other
agencies for sourcing components, to deliver the outline envelope drawing and
then the equipment took some effort on the part of the design team members.
We had gone for the best or near best
suppliers with proven credentials. We had ordered for two rakes only;
components like high speed Pantograph, roof-mounted 25KV cable and isolator
systems, solid state devices etc. were required in small numbers/quantities. Many
a time any extent of assurances or incentives to these suppliers did not work
in our favour to get the material on time. There was also the issue of dealing
with competing suppliers within the team and this had its own disadvantages as
dynamics amongst them, at times, time becomes unpredictable, governed by some
extraneous factors; I know it may sound frivolous but I left all this this as
the sole preserve of the cool and composed, Mr. Tranquillity, Sri D.P.Dash, the Chief Design
Engineer/Elect. And I was told he handled it smoothly, frequent pin pricks
et al. All I know is that he was able to create a synergy amongst all such
vendors and sub-vendors to minimise the tussles at various stages of manufacture.
At the end of the day, the takeaway here once again is that it is all about
positive human interaction; it matters the most and works most of the time.
After the shop floor meetings, all the
participants were invited for dinner at my bungalow. One ticklish issue was
solved during dinner after the main representative of one of the competing
firms forced me to sing Jim Morrison of the Doors with him.
The participants had to suffer some fervid but pathetic singing and I am sure
this time it was not Firaq but Morrison turning in his
grave. And soon, Sri Dilip, the Dy. Chief
Mechanical Engineer/Design, would do his monstrous pirouetting and shaking
and all the left over problems of the day would vanish in thin air.
Sri
Srinivas, the Chief Design Engineer/Mech.
was struggling with some issues with the toilet as soon as the first coach
was provided with one. The toilet was meant to be a unique combination of
vacuum evacuation with bio-tank. Someday India would see the prevalent system
of vacuum evacuation from toilets to collection tanks which are further
evacuated at maintenance depots but many roadblocks, some real and some
perceived, have kept this system out of our trains. Be that as it may, the
toilets were designed to look and function, conceptually, as under:
Some other
issues, which were being addressed in parallel, were, 1) the design somehow
incorporated a small ramp in gangway area; now, this had come for a lot of
criticism in the first air-con EMU manufactured by ICF. This had to be modified.
Eventually, the coupler height was reduced to 940 mm against the standard 1105 mm
for IR; both the driving end, however, provided for 1105 mm to cater to the
requirement of haulage by a locomotive in any unforeseen situation. By the way,
the fully sealed double layer gangway needed more end-to-end space and the overall
coach length had earlier been reduced by 440mm (23100 against 23540), 2) automatic
plug door with sliding foot step required that the design and manufacturing jigs
be redone, shifting the doorway to coach ends to accommodate the sliding step,
3) due to low roof in TC with Pantograph, a very sleek AC duct was redesigned
to maintain head room for luggage rack, and so on.
A recap,
before I talk a bit about design and manufacture of the bogie, which, to my
mind was the most crucial part of the project.
Let me
state in broad terms as to what had been achieved so far:
·
Recognizing the immense potential of team
ICF, we had started with the concept on our own and put it together for the decision-makers
to understand the doers to appreciate.
· We the sanction from the then CRB, Sri
A.K.Mital, in the face of stiff opposition. Opposition? Yes. And reverting
to the theme of internecine warfare between departments in IR, opposition by
whom? By Mechanical department; the department, incidentally, set to benefit
the most if Train 18 became a success! Such is indeed the state of affairs in IR.
So what was needed to be done, I
can say without batting an eyelid, was to ignore these jealous naysayers, top
to bottom, and that was done in toto.
·
We got a multi-disciplinary team going
without any departmental wrangles and squabbles.
·
We appointed consultants where our own capability
was suspect but kept detailed design totally with respective design wings of
ICF; we did not allow any disabling ToT(transfer of technology) and all the IPR (intellectual property
rights) was the property of ICF.
·
Got the blessings of the one who mattered and
understood what we were up to; in this case, the then CRB, Sri Ashwani Lohani, who had been
consistent and unwavering in supporting us.
·
Any negativity or lack of courage of
conviction was eliminated through some crackerjack handling by senior team
members; a whole lot of equipment were ordered on single tender! We never
tendered for tendering sake (tendering without an eye on delivery, as many
of us unfortunately do and do it even today as I write).
·
We ensured that we had a leader in the 2nd
IC, first Sri L.C.Trivedi (current
GM/ECR, earlier PCME/ICF) and then Sri
Shubhranshu (the next PCME/ICF), without which it would have been extremely
difficult to execute the project.
·
We treated participating industry as partners.
We held key pep up meetings first in Design office and later on shop floor.
·
We monitored time lines very closely at the
level of GM/PCME level.
· We involved
RDSO Train Set and Testing directorates as they would be testing the train for
roadworthiness, safety, ride quality and oscillations etc; in fact, creation of
the Train set directorate is an offshoot of this project, pushed strongly by ICF
with a view to consolidate our effort in an organization which could act as the
wellspring for train sets in future.
· And above
all, we all made conscious efforts to keep the morale of the entire team very
high with free flowing smiles and only occasional frowns.
Thanks to
a Press & Media workshop held at ICF at the instance of the then CRB, a buzz had already been created in
respect of Train 18. Although the workshop was held to educate the participants
on various aspects of legacy, strengths and working of IR, some special
interest by the former in the projects of ICF was natural. Extensive coverage
had, therefore taken place on Aaj Tak/India Today, Zee Business, Door
Darshan, Financial Express and Times of India etc. This generated some additional
pressure for early turnout.
Enough hype
and publicity. The proof of the pudding is in the eating! When would we able to
serve the pudding? Hey, did you catch me agreeing with Mr. Ford
when he said, in Shakespeare’s The Merry Wives of Windsor that it was better
to be three hours too soon than a minute too late? I was now
learning to change tack and quote Frair Lawrence
from Shakespeare’s Romeo and Juliet, rather shamelessly, “Wisely and slow. They
stumble that run fast.” Was Shakespeare an inspiration for business leaders
or the last resort of those who bluster a lot but manage poorly? Take your
pick!
Were we worried?
No and not without reason although someone would soon show me the mirror,
perhaps through the poet Dagh:
Aap ka aitbar kaun
kare,
Roz ka
intezar kaun kare.**
** Who is
now willing to believe you, who would keep waiting for you?
Hello,
ReplyDeleteThis is great Article. Keep Up the growing good work.Album Ecological Resort
nice blog..
ReplyDeleteSteel Suppliers in Chennai
artificial arms delhi
ReplyDeleteBeing one of the reputed artificial limb (prosthetic arms and legs) fitting centers in India, we offer prosthetic legs and prosthetic arms to assist people to regain their freedom
to get more - https://www.ottobock.in/
Here is Mr Benjamin contact Email details,lfdsloans@outlook.com. / lfdsloans@lemeridianfds.com Or Whatsapp +1 989-394-3740 that helped me with loan of 90,000.00 Euros to startup my business and I'm very grateful,It was really hard on me here trying to make a way as a single mother things hasn't be easy with me but with the help of Le_Meridian put smile on my face as i watch my business growing stronger and expanding as well.I know you may surprise why me putting things like this here but i really have to express my gratitude so anyone seeking for financial help or going through hardship with there business or want to startup business project can see to this and have hope of getting out of the hardship..Thank You.
ReplyDeletenice post..
ReplyDeleteCeramic Tiles Dealers In Chennai
Kitchen Sink Dealers In Chennai
Johnson Dealers In Chennai