Quo Vadis, Private Train? Don’t let this train derail!
Quo Vadis, Private Train? Don’t let this train derail!
The
last time I wrote on the subject was on 8th November, 2020. I had
written that, assuming that the entire exercise by Indian Railways (IR) was not
about, first boiling the ocean and then blamestorming, but hopefully more like
doing nothing by halves, certain sine qua non had to be spelt
out. Summarizing, I had mentioned that it appeared that there was no risk
for Indian Railways (IR), except loss of face in case of failure of the project
whereas a prospective PTO (Private Train Operator) had to contend with high
risks and perhaps even perpetual losses. At stake was not merely this project
but long-term credibility and allure of IR, both from the standpoints of ease
of doing business and long-term PPPs into the future. IR could not afford the
smug luxury of a premise that it was dispensing favours, not looking for a
partner in success. This privatization project was being seen as a very welcome
move of IR to liberate itself from its proverbial stick-in-the-mud stance and
it should not be allowed to fail due to cocksure rigidity and a flawed PPP
architecture. It was time for IR to open the kimono and meet the prospective
bidders halfway. So, let us review where we stand
today.
This is a first step towards a viable and vibrant private train operation in India. We must remember that it is the strategic vision of entering, as early birds, in a field which holds promise for future which would drive the prospective bidders. A long wish list for making the bid documents more friendly for investment may not be of much use at this stage as IR is already too far gone with their bid documents so let us leave it at that.
Governments are mortally afraid of windfall profit to the concessionaires as it quickly educes accusations of venal wrongdoing and therefore some reluctance to change things that would seem to benefit the bidders is natural. But it should not be allowed to wither away to paranoia. I am sure things would mature into a pragmatic model as we move along this path but at this stage, the project is obviously fraught with multiple risks and many imponderables. On the other hand, given that It is difficult to participate in this project purely on the basis of NPV/IRR calculations with so many elements of incertitude, IR must still address the main concerns of the prospective bidders. As per Corrigendum No. 1 of 30th December 2020, the bid submission due date is 31.03.2021, extended from the earlier one in end January 21. The bid documents for RFP call for commissioning of prototypes in about 31 months after appointment of the PTO, and with successive induction of rakes, completion of the entire operation in about 66 months. Well, the project timeline is fine and may even be compressed. The time available for bidding, however, which would involve working out a financing plan, selection of rolling stock and then preparing a detailed commercial analysis for submitting a competent and viable bid, is still far from adequate. Thorough analysis of each cluster requires a minimum of 3 weeks and even if a bidder quotes for, say, 4 clusters, they would run out of time before submission. IR must address this seriously as a delay of couple of months would not be as injurious as a failed or half-baked exercise.
Some changes have indeed been accepted by IR but that
is now history. To my mind, some of the issues, inter alia, to be addressed
are, 1) The contract period of 35 years
is a killer. A strong pitch must be made for reduction of the project duration
to 24 years. 2) The PTO should be given more freedom to choose his train’s
departure or arrival time as well the origin and destination within a city
based on his estimation of preferences of the passengers. 3) The documents say
that obligation of the Government to provide exclusivity shall not apply once
the capacity utilization of a train crosses 80%. This is like penalizing a PTO
for good performance; this limit of utilisation needs to
be increased to 95% for each route in all the clusters. 4) IR should allow
the concessionaire to choose the routes they would like to operate anywhere between
70% and 100% of the specified routes so the risk of operation on unviable
routes is mitigated and 5) The exit clauses and penalties should be re-examined
as no PTO would like to exit after investing in rolling stock. After all, the
rolling stock would be almost like dead assets which he would not be able to
sell off like other assets and lastly but perhaps most significantly, 6) A gross revenue share of 10%, as assumed in the DFR projections has the
making of a futile long walk.
Prospective
bidders have repeatedly raised concerns about a severe impact of this on financial
viability which ironically, has IR charging haulage charges (access charges, in
reality) and still looking for a share in revenue. A share in profit could be
somewhat more realistic but IR is, rightly or wrongly but understandably averse to this due to
apprehensions of manipulations. One way could be to consider negative
bids such that while IR is relieved of any investments in unpopular sectors, the
government bears a sort of subsidy burden to relieve the PTO of the risks of a
seemingly unremunerative sector. The government may even consider reimagining
the model by reducing the haulage charges from the gross revenue. Learning from
Infrastructure, Highway and Telecom sectors, which have come a long way since
the inception of their PPP models, can
come in handy to pinch the bid conditions towards something more amenable for
receiving good participation. IR must
consider ameliorating this important aspect.
The issue of an independent regulator has been echoed
by all the prospective bidders repeatedly. The document calls that the
Government would appoint a consulting engineering firm to be the independent
consultant under this agreement (the “Independent Engineer”). This is a clause
which the prospective bidders find the most disturbing. In this environment of
multiple risks and limited possibilities of risk mitigation, it is absolutely
essential that an independent regulator with a mandate to adjudicate and resolve be in place.
As for the assessment of various clusters in terms of
viability, it is also a matter of detailed study. All one can say is that each
cluster has some very popular routes and some very unpopular routes. That is
why the suggestion of freedom to a PTO for a min of 70% to 100% operation in a
cluster.
I would not like to speculate on the likely outcome of
bidding if the ticklish issues do not get addressed and resolved. As things
stand, there should be a moderate response with some clusters getting many bids
and some may even go without any bids. But whatever be the outcome, one certainly
hopes that in spite of most of the prospective bidders sitting on the fence
today, at the end of the day, a win-win situation would emerge.
Good analysis.
ReplyDeleteI have few questions.
a) Impact of HSR introduced in some of the routes in the next 5-10 years.
b) With COVID, Work From Home and mandate for wide-spread development, why not allow running of smaller trains at more frequency, say hourly, in dense traffic routes.
c) The current proposition of volume/scale doesn't look viable at all. An organisation to sustain needs 1000+ cores annual revenue, else they would lose interest, unless they cross-subsidise from other businesses for strategic reasons.
I agree. It's more about looking at the future and throwing your hat in the rink.
DeleteGood analysis sir,
ReplyDeleteWith respect to the PTO project, I wanted to understand how to compare a Push pull train vs a train set? I understand that, Train 18 was a 100 Cr train set for 16 coaches and a push pull could be cheaper (more lucrative for a operator).
A major advantage for train set would have been acceleration but a push pull train could achieves it at lower cost.
Well, it's a complicated subject. You can approach me on smani58@hotmail.com for a detailed discussion. Thanks
ReplyDelete