Train 18 series, part VI..everyone aboard!
So, where had we reached as we crossed early days to mid 2017? Our Design, Procurement (called stores on IR) and Finance teams had started working with greater camaraderie and cooperation and this had shown results. The consultancy contracts were in place and the crucial procurement contracts were in various stages of completion. ICF officers at this stage were overloaded with regular, incremental and project works. Most of the ace officers were overworked but then I also saw them doing their jobs with a smile. Why were they overloaded? Let me attest for you the basket of tasks at hand at ICF; while Train 18 project was definitely the bellwether, we had some very significant works in hand, e.g., stopping production of ICF design coaches and switch over completely to LHB design even as the overall production was to be increased from 2277 to 2500 coaches, design and manufacture of world class DEMUs for Sri Lanka, design and manufacture of MEMUs, both with on-board and under-slun...