Dash and the last mile dash(before the turn out of Train 18)
Friends, this is an account of those heady days when last-minute hectic activities were on at ICF to turn out Train 18 latest by the third week of October, 2018. The Chennai firm, the protagonist as far main furnishing, nose cones, cab and toilets were concerned, had picked up speed and it appeared that, should we start receiving the second to fifth Transformers in the second week of October, it would be possible to turn out the rake by the end of the third week of October, employing what I would call the Dash recipe of testing a self-propelled train . Second to fifth because the first one was under extensive testing. Dash had planned to start assembling the second Transformers onwards and keep the train ready for testing as soon as the first Transformer cleared the tests. Massive infrastructural preparation works had to be taken up for the test and validation of Train 18. A self-propelled train has to be tested as a train after all the coaches are coupled. Our comm...